ROC Latency Budgeting Template (Excel)
The ROC Latency Budgeting Template (Excel) is a structured spreadsheet tool used in the design and validation of Mine Remote Operations Centers to quantify, allocate, and track end-to-end latency contributions across telemetry, control, video, and audio signal paths. It enables engineers to ensure total system latency remains within operational safety and performance thresholds—typically ≤500 ms for critical teleoperation loops. The template supports traceability from physical layer components (e.g., radios, encoders) to application-layer protocols (e.g., MQTT, RTP, OPC UA).
📖 Overview
📑 Key Components
🎯 Applications
- ✓ ROC system architecture validation during FEED (Front-End Engineering Design)
- ✓ Vendor proposal evaluation for network infrastructure and edge compute hardware
- ✓ Operational readiness assessment prior to ROC commissioning and crew training
📐 Key Formulas
Total End-to-End Latency
Σ(Propagation_Delay + Serialization_Delay + Processing_Delay + Queuing_Delay + Jitter_Buffer_Delay + Application_Overhead)
Sums all deterministic and statistical latency contributors across the signal path
Latency Margin
Allowable_Latency − Measured_or_Budgeted_Total_Latency
Quantifies remaining headroom before violating operational threshold
Uncertainty-Adjusted Budget
Allocated_Budget × (1 + Uncertainty_Factor)
Applies conservative scaling to account for environmental or implementation variability (e.g., 0.15 for LTE-R link fluctuations)